Aug 3, 2023
This week we took another step toward making our congregation’s buildings more beautiful, accessible, and useful for creative, courageous, and compassionate ministry.
On Tuesday, Pastor Mike Wilker met with Chris Baier from Joseph Construction and Lee Anderson from Kueny Architects to open the bids on the sanctuary reconstruction project. The approximate cost of the project is $827,000.
This total includes demolition, concrete, steel fabrication, steel installation, carpentry, drywall around the posts, flooring repair where the old posts were, painting, plumbing (radiators along west wall), and some electrical work near where the posts will be installed. It does not include reshingling the roof holes where the steel rafters will be inserted.
Roughly, that leaves $3.6 million for the Gathering Hall and possible geothermal and solar expansion from the $4.4 million construction budget. In addition indirect/soft costs are about $1 million and include architect and engineer fees, contingency (about 10%) sanctuary furnishings, livestream, AV, etc.
Next Steps:
- The construction manager will work to get a bid for shingling.
- The construction manager and architect will review the bids in more detail. The construction manager will put together a full bid report for the Pre Construction Team.
- Pastor Mike will call a Pre Construction Team meeting within the next week so the construction manager and architect can review the bids with the Team and they can make a recommendation to the Council.
- Council will receive and act on the Pre Construction Team recommendation. The next regular Council meeting is Tuesday, August 8. We doubt that the Pre Construction Team will be able to meet in time for them to have a recommendation by Tuesday’s meeting (maybe?). So, this may need to be a special Council meeting.
- If the Council approves the contracts, then the steel fabricator needs six weeks to create shop drawings.
- Then the construction manager and architects review and approve the shop drawings.
- Once the shop drawings are approved, it will take 4-6 weeks to fabricate the rafters and posts.
- Then construction can begin. Although this technically could begin mid-December, Pastor Mike, the architect and construction manager think it’s better to begin sanctuary construction after January 1.
- So for the first part of 2024 we will worship either in the Fellowship Hall or Fireside Room, depending on the stage of construction.
Other steps and some questions:
- Kueny Architects is currently working on revised drawings of the large Gathering Hall. That project will be ready to be released for bids around August 18-21. The bids will be due around September 19-21. Then we’ll go through a similar process to above. The big decision will be whether the large Gathering Hall can be built for $3.6 million. The Pre Construction Team and the Council will probably be able to decide on the Gathering Hall construction by mid-October. To see the revised scheme for the Gathering Hall, you can view a recording of last week’s Pre Construction Team meeting by clicking on this Zoom link. https://us02web.zoom.us/rec/share/AfEvi97nGeR18V-VUY4OYhJHAjcBiXK-U9H6Knz-LHtmb8uBdg02-0hq9xQs7Mtg.bgvLmCYVpuTLI1e0 Passcode: #zA2FAm+
- Pastor Mike recommends that the Council and Preconstruction Team host congregation information sessions in August about the Sanctuary and in October about the Gathering Hall.
- In later August or early September, Pastor Mike would like to convene a meeting of the Fundraising and Finance Team to prepare for and to begin implementing the Roof Raising and Ground Breaking phase of the Campaign in the Fall and Winter.
- We will formally apply for the Mission Investment Fund loan at least six weeks before construction begins. We have a pre-approval now. Once we have a construction budget and form a building contract(s) then we can lock in a loan rate. Although we are pre-approved for up to $1.7 million, we only withdraw what we need as we need it. We only need to pay interest during the construction; once construction is complete we pay principal and interest.
- Pastor Mike will contact contractors regarding the sanctuary furnishings, AV, and livestream systems. The architect and construction manager will coordinate with those contractors. That work will be done after most of the construction work is completed.
- The construction manager said that one of the first construction steps of the Gathering Hall project will be excavating for the elevator. That will probably need to wait until April 2024 (Easter is March 31, 2024). So most of the Gathering Hall construction will be Spring-Fall 2024, it appears.
Thank you! We are getting closer to having a building that reduces barriers so more people can welcome and gather together to praise God, care for one another, grow in faith, and serve the world God so dearly loves.
Peace be with you,
Pastor Mike
Jun 29, 2023
Capital Campaign Update
June 29, 2023
Pastor Mike Wilker
The For Generations to Come Capital Campaign The Preconstruction Team, architects, and construction manager have been working in the past four months to craft an updated construction plan. We are working hard to balance the construction expenses and income. This week the team decided to separate the plan into four bid projects: 1) Sanctuary steel structure, 2) Sanctuary finishes, 3) Gathering Space, and 4) Elevator and small entry. This will help the team and Council determine which parts of the project we will be able to accomplish and how much each component will cost. The new bids will be due later this summer.
Projected Income
We have already received $3 million in gifts and pledges! If we have the financial capacity to build the large Gathering Hall, there may be an additional possibility of $600,000 for geothermal and expanded solar. Thank you! As we enter the groundbreaking phase, we will ask for another $700,000 in gifts. In addition, we’ll use the undesignated bequests of $112,000 for sanctuary furnishings, AV, and livestream equipment. Plus, we plan to have a $1 million loan to finance up to 30 years. This makes the total estimated campaign income $5.4 million.
Expenses
On the expense side, the indirect costs like fees for architects, engineers, sanctuary furnishings, permit fees, and contingency funds will be about $1 million. That leaves $4.4 million for actual construction and remodeling costs.
Bids and Revisions
The base bid for the Sanctuary restructuring, addition of the Gathering Hall, remodeling of the first floor of the office/education wing, and geothermal wells was $6.5 million. We selected Joseph Company from Austin, MN, to help us reduce the costs of the base bid to get us to $4.4 construction.
At the end of May, the architects and construction manager presented their proposal to cut the construction costs from $6.5 million to $4.4 million. Among many smaller reductions that seemed achievable, the biggest cut they recommended was to postpone the remodeling of the office and education wing until a later phase. Even with that cut, the project would cost $5.9 million, $1.5 million more than our estimated gifts and loan.
The Preconstruction Team gave the architects and construction manager more time to rework their drawings and recommendations.
On Tuesday, June 27, the Preconstruction Team met with the architect and construction manager to receive updated concepts and timelines for bidding and construction. We accepted the following:
FIRST LUTHERAN CHURCH – BID PACKAGE OUTLINE
Bid Package #01 – Sanctuary Steel Bid July 2023
- Install new Sanctuary structural steel truss frames.
- Install new Sanctuary steel columns–Chase down through lower level.
- Patchwork associated with new steel Sanctuary level.
- Patch work associated with new column install main and lower level.
- Replace steel cat walk in attic space of Sanctuary.
- Rework affected baseboard heat for Sanctuary.
Bid Package #02 – Sanctuary Finishes Bid dates TBD (Fall/Winter 2023)
- New paint work in Sanctuary.
- Painting of existing chair rail.
- New sanctuary lighting package–revised design 2023.
- Platform alterations and North Sanctuary ramp.
- Sanctuary flooring and wall base.
Bid Package #03 – Gathering Space Bid dates TBD (Fall/Winter 2023)
- Gathering Space and West Entrance construction.
- New Gathering Space Restrooms. Minimum (4) restrooms.
- New elevator construction.
- Installation of Sanctuary door from elevator landing.
- Lower level elevator landing to Fellowship Hall.
- Reduce Gathering Space kitchenette to a beverage counter.
- Existing first floor offices and Fireside Room remain unchanged.
Bid Package #04 – Elevator and Small Entry Design Bid dates TBD (Fall/Winter 2023)
- Sanctuary Entrance Construction (Design Option“02”–Entrance on existing grade).
- New Sanctuary Entrance Exterior Sitework.
- Elevator Construction.
- West Office Entry and Vestibule Construction –wayfinding signage in hallway.
- West ADA sidewalk from parking lot.
- Installation of Sanctuary door from elevator landing.
- Lower level elevator landing to Fellowship Hall.
- Existing first floor offices and Fireside Room remain unchanged.
Sanctuary A/V, livestream, and furnishings will be bid separately and are paid from the indirect costs budget.
May 18, 2023
It’s planting time here in NE Iowa, and lots of us are busy readying our garden beds. Many of us pick plants that would grow well in a particular sun or shade site; some of us pick flowering plants that will be beautiful in our annual and perennial beds. The environmental problem is the use of chemicals to treat farm crops. Many garden plants for sale, particularly at big-box stores, have been pre-treated with insecticides and pesticides that harm and even kill pollinator species, which include some birds and bats, but the greatest number are insects: bees, butterflies, flies, wasps, and beetles. To fight this problem is a big job, but each of us can do our part by being careful that we purchase, preferably at greenhouses, native and pollinator-friendly flowers. It’s also helpful to make nest sites available, avoid using pesticides yourself, and spread the word to others about these steps. What plants are both native and pollinator-friendly in our area? There is a long list that includes various types of milkweed, clover, thistle, blazing star, coneflower, ironweed, dropseed, sumac, aster, goldenrod, and phlox. Various websites have much more specific lists: one pdf. list for the Midwest is at the following site: https://xerces.org/sites/default/files/publications/22-025_01_NPPBI%E2%80%94Midwest_web.pdf.
What about pesticides? The most common problematic insecticides to know about are neonicotinoids and glyphosates. Farmers use neonicotinoids to control sucking insects. Because neonics are systemically absorbed, they can affect all plant parts, including the blossom and pollen. They then attack the nervous system of the pollinator; this is considered by many to be the cause of the current epidemic of honeybee hive collapse across the country. Glyphosate is another synthetic chemical used in many herbicides, including Roundup, which is applied to agricultural crops but also used in lawns and gardens to control broadleaf weeds and grasses. The EPA considers this chemical unlikely to be carcinogenic to humans, but many lawsuits have claimed that the chemical caused non-Hodgkin’s lymphoma. For that reason, some companies have taken these products off the market. There is a strong argument that the use of glyphosates caused a drastic drop in the population of an important pollinator, the monarch butterfly, by eliminating its primary food source, milkweed. As the use of glyphosates increased and milkweed died out, the count of monarchs dropped drastically.
Mar 30, 2023
It’s crucial that each of us develops the habit of stopping to think each time we dispose of something. If the item is single-use plastic, let’s ask ourselves how we might have avoided getting it in the first place. If it’s something else, let’s ask ourselves if it would be recyclable. If yes, transfer it to a recycling receptacle. Is this something that can be repaired and reused? Is this something that could be used by someone else? If yes, sell it (for example, to the Get-Up), donate it (Depot, Goodwill) or give it away (join the Facebook group Buy Nothing Winneshiek County, IA) or gift it to someone you know who can use it. Let’s try to remember that whatever we place in our home garbage is destined for the landfill.
Sanitary landfills are a necessary but not ideal solution to the problem of waste. They are scientifically engineered facilities constructed in the ground and designed to hold and isolate waste from the environment. Federal and state regulations govern the location, design, and operation of landfills in order to protect human health and the environment. We put our garbage into the ground. Each landfill takes space away from other uses—it cannot be used for agriculture, housing, or recreation in nature. Its size is finite: think of the landfill as an underground permanent garbage bin that is never opened or dumped. When it is full, the county needs to develop a new site. Although regulation landfills are designed to prevent any leaking, some landfills can still leach toxic chemicals into ground or surface water. As any biodegradable organic waste decomposes (wherever it is), it naturally releases methane, a potent greenhouse gas that absorbs heat and is a major contributor to climate change.