This week we took another step toward making our congregation’s buildings more beautiful, accessible, and useful for creative, courageous, and compassionate ministry.
On Tuesday, Pastor Mike Wilker met with Chris Baier from Joseph Construction and Lee Anderson from Kueny Architects to open the bids on the sanctuary reconstruction project. The approximate cost of the project is $827,000.
This total includes demolition, concrete, steel fabrication, steel installation, carpentry, drywall around the posts, flooring repair where the old posts were, painting, plumbing (radiators along west wall), and some electrical work near where the posts will be installed. It does not include reshingling the roof holes where the steel rafters will be inserted.
Roughly, that leaves $3.6 million for the Gathering Hall and possible geothermal and solar expansion from the $4.4 million construction budget. In addition indirect/soft costs are about $1 million and include architect and engineer fees, contingency (about 10%) sanctuary furnishings, livestream, AV, etc.
Next Steps:
- The construction manager will work to get a bid for shingling.
- The construction manager and architect will review the bids in more detail. The construction manager will put together a full bid report for the Pre Construction Team.
- Pastor Mike will call a Pre Construction Team meeting within the next week so the construction manager and architect can review the bids with the Team and they can make a recommendation to the Council.
- Council will receive and act on the Pre Construction Team recommendation. The next regular Council meeting is Tuesday, August 8. We doubt that the Pre Construction Team will be able to meet in time for them to have a recommendation by Tuesday’s meeting (maybe?). So, this may need to be a special Council meeting.
- If the Council approves the contracts, then the steel fabricator needs six weeks to create shop drawings.
- Then the construction manager and architects review and approve the shop drawings.
- Once the shop drawings are approved, it will take 4-6 weeks to fabricate the rafters and posts.
- Then construction can begin. Although this technically could begin mid-December, Pastor Mike, the architect and construction manager think it’s better to begin sanctuary construction after January 1.
- So for the first part of 2024 we will worship either in the Fellowship Hall or Fireside Room, depending on the stage of construction.
Other steps and some questions:
- Kueny Architects is currently working on revised drawings of the large Gathering Hall. That project will be ready to be released for bids around August 18-21. The bids will be due around September 19-21. Then we’ll go through a similar process to above. The big decision will be whether the large Gathering Hall can be built for $3.6 million. The Pre Construction Team and the Council will probably be able to decide on the Gathering Hall construction by mid-October. To see the revised scheme for the Gathering Hall, you can view a recording of last week’s Pre Construction Team meeting by clicking on this Zoom link. https://us02web.zoom.us/rec/share/AfEvi97nGeR18V-VUY4OYhJHAjcBiXK-U9H6Knz-LHtmb8uBdg02-0hq9xQs7Mtg.bgvLmCYVpuTLI1e0 Passcode: #zA2FAm+
- Pastor Mike recommends that the Council and Preconstruction Team host congregation information sessions in August about the Sanctuary and in October about the Gathering Hall.
- In later August or early September, Pastor Mike would like to convene a meeting of the Fundraising and Finance Team to prepare for and to begin implementing the Roof Raising and Ground Breaking phase of the Campaign in the Fall and Winter.
- We will formally apply for the Mission Investment Fund loan at least six weeks before construction begins. We have a pre-approval now. Once we have a construction budget and form a building contract(s) then we can lock in a loan rate. Although we are pre-approved for up to $1.7 million, we only withdraw what we need as we need it. We only need to pay interest during the construction; once construction is complete we pay principal and interest.
- Pastor Mike will contact contractors regarding the sanctuary furnishings, AV, and livestream systems. The architect and construction manager will coordinate with those contractors. That work will be done after most of the construction work is completed.
- The construction manager said that one of the first construction steps of the Gathering Hall project will be excavating for the elevator. That will probably need to wait until April 2024 (Easter is March 31, 2024). So most of the Gathering Hall construction will be Spring-Fall 2024, it appears.
Thank you! We are getting closer to having a building that reduces barriers so more people can welcome and gather together to praise God, care for one another, grow in faith, and serve the world God so dearly loves.
Peace be with you,
Pastor Mike